relevant costForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › relevant costThis topic has 1 reply, 2 voices, and was last updated 5 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total) AuthorPosts January 22, 2019 at 12:56 pm #503009 kennigaraParticipantTopics: 181Replies: 242☆☆☆Hi my dear tutor, i have a question. do we consider rental cost and lease pays as relevant cost or committed cost? January 22, 2019 at 5:14 pm #503042 John MoffatKeymasterTopics: 56Replies: 53865☆☆☆☆☆It depends on what the wording of the question is.If they are extra costs as a result of doing the new work, then they are relevant costs. If they are existing costs that do not change, then they are not relevant costs.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In