• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

June 2018 Ruva

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › June 2018 Ruva

  • This topic has 3 replies, 2 voices, and was last updated 6 years ago by John Moffat.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • November 29, 2018 at 11:20 am #486401
    Anonymous
    Inactive
    • Topics: 1
    • Replies: 1
    • ☆

    Hi Sir John Moffat,
    1) what is the discount rate for phase 1 and phase 2? I use all equity cost of equity engaged same as project E at 12% and apply in MM prop 2 (tax) and obtain new WACC. And I got 11%.
    2) Is the scenario in Ruva project E an option to expand rather than option to delay? For construction industry, normally it would’ve been option to abandon.
    3) investment 320m in year 4 for phase 2 would be discounted at 5% kd as per question.
    I got negative NPV with cost of debt but positive NPV if discounted at WACC 11%.

    If cost of debt is more reasonable, what is the reason for this? Do I make assumption that the reason is cos investment 320m is entirely financed out from debt financing with outlook that soft capital rationing limits the investment? Also optimum capital structure at best with increase of debt and obtain the tax benefit.

    Therefore reject Project E on director’s proposal .

    4) how real options build on NPV when evaluating investment decision?
    It considers uncertainty in the future and add/reduce the value to have the option to expand/delay over time and volatility of project as compared to without the option. Hence BSOP model is used on phase 2 and traditional NPV on phase 1. Extra investment undertaken if PV> investment.

    November 29, 2018 at 2:53 pm #486423
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    Please check you are referring to the correct exam – there is no question called Ruva in the March/June hybrid questions.

    November 30, 2018 at 11:08 am #486561
    Anonymous
    Inactive
    • Topics: 1
    • Replies: 1
    • ☆

    Here is the scenario :
    Project E is two phase project.
    Phase 1 initial outflow immediately and cash inflows earned.
    Phase 2 investment $320m at start of year 5. Annual inflation adjusted after tax cash inflows $50m. Phase 2 will be sold at end of 10 year life for $50m. Uncertainty for these cash flows and volatility standard deviation given.

    Ruva MV debt to equity ratio 40:60.
    Cost of debt 5%. Risk free rate 3%.

    Project E is not normal business of Ruva and all equity of co industry similar to Project E is 12%.

    Ruva CEO believes that phase 2 investment $320m should be discounted at cost of debt, better estimate of its opportunity cost.
    ——
    I managed to figure out for q4. In addition to above questions,
    How to estimate the value of project E
    if not delay decision?

    My answer:
    (i)PV cf in
    pHase 1 discounted at wacc using MM proposition
    + phase 2 investment 320m at kd
    + Phase 2 cash inflows include sale of project E at Kd ( instead of WACC like in phase 1)

    November 30, 2018 at 3:47 pm #486588
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    Sorry, but again – this is not a published ACCA question (and you surely have an answer you check to?)

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • The topic ‘June 2018 Ruva’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • bizuayehuy on Interest rate risk management (1) Part 1 – ACCA (AFM) lectures
  • sokleng on FM Chapter 7 Questions – Investment appraisal – methods
  • Annabelayinloya on IFRS 16 Identifying a lease – ACCA (SBR) lectures
  • Ojoggo on The Statement of Financial Position and Income Statement (part a) – ACCA Financial Accounting (FA) lectures
  • hhys on PM Chapter 4 Questions Environmental Management Accounting

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in