indirect costForums › ACCA Forums › ACCA MA Management Accounting Forums › indirect costThis topic has 1 reply, 2 voices, and was last updated 6 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts September 21, 2018 at 7:06 pm #475470 kingkongsajangMemberTopics: 95Replies: 75☆☆why is plant hire for long term contract a direct cost and not an indirect cost?Kind regards September 22, 2018 at 6:42 am #475492 John MoffatKeymasterTopics: 57Replies: 54479☆☆☆☆☆Because it is specifically for the contract and not a general overhead that is shared by all their jobs.In future, if you want me to answer you must ask in the Ask the Tutor Forum.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)The topic ‘indirect cost’ is closed to new replies.