• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March 2026 exams.
Get your discount code >>

Solution for Example of Bottleneck resource in notes

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Solution for Example of Bottleneck resource in notes

  • This topic has 1 reply, 2 voices, and was last updated 7 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • September 13, 2018 at 3:25 pm #474506
    Anonymous
    Inactive
    • Topics: 1
    • Replies: 0
    • ☆

    5. Bottleneck Resource
    In practice, it is likely that a product will have to be worked on by several machines – one after the
    other.
    The rate of production will be restricted by the slowest of the machines, and this machine is known
    as the bottleneck resource.
    The calculations that we have been through in the earlier examples will be performed using the
    hours per unit in this bottleneck resource.
    Example 3
    Yam Co is involved in the processing of sheet metal into products A, B and C using three processes,
    pressing, stretching and rolling.
    The factory has 50 production lines each of which contain the three processes: Raw material for the
    sheet metal is first pressed then stretched and finally rolled. The processing capacity varies for each
    process and the factory manager has provided the following data:
    Processing time per metre in hours
    Product A Product B Product C
    Pressing 0.50 0.50 0.40
    Stretching 0.25 0.40 0.25
    Rolling 0.40 0.25 0.25
    The factory operates for 225,000 hours.
    Identify the bottleneck process and explain why this process is described as a ‘bottleneck’.

    September 14, 2018 at 8:26 am #474541
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54814
    • ☆☆☆☆☆

    Why have you copied out the whole question like this???

    The answer is in the free lecture notes. Look at the contents page to find them – the answers to all of the examples are printed in the lecture notes!!

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • The topic ‘Solution for Example of Bottleneck resource in notes’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • ascenderkid on ACCA BT Chapter 15 – How an individual can develop – Questions
  • MAC2026 on MA Chapter 3 Questions Presenting Information
  • MikeLittle on Company Law – Directors – Statutory Duties – ACCA LW Global
  • annas3429 on Company Law – Directors – Statutory Duties – ACCA LW Global
  • Kim Smith on What is Assurance? – ACCA Audit and Assurance (AA)

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in