Question No 3: Which of the following environmental accounting techniques would be relevant when considering the costs of dismantling machines at the end of a project?
a. Activity Based Costing b. Flow cost accounting c. Input / Output analysis d. Lifecycle costing
I chose Lifecycle costing, but the popup said the answer is Flow cost acounting.
lifecycle costing includes the cost of disposal or waste and so does flow cost accounting, where did I go wrong?