Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Work-in-progress
A company operates a process in which no losses are incurred. The process account for last month,when there was no opening WIP,was as follows:
Costs arising. 624000
Finished output(10000units) 480000
Closing WIP (4000units) 144000
The closing WIP was complete to the same degree for all elements of cost.
What was the percentage degree of completion of the closing WIP?
Answer is 75%..
Sir can you explain how we got that answer…
The cost per unit of the finished output is 480,000/10,000 = $48
The cost per unit of the closing WIP is 144,000/4,000 = $36
Therefore the degree of completeness must be 36/48 = 75%
Do watch my free lectures on this – the lectures are a complete free course for Paper F2 and cover everything needed to be able to pass the exam well.
Thnku so much sir…
You are welcome 🙂