- November 20, 2017 at 1:19 am #416779
The management accountant of a business has identified the following information.
Activity level 800 unit 1200 unit
Total cost $ 16400 $23600
Fixed cost of the business set up by 40% at 900 unitWhat is the variable cost per unit?
Sir i dont understand which method to calculate i saw my book but there is very confusing method sir please tell me how to do this question?
November 20, 2017 at 8:34 am #416820You need to use a bit of simple algebra.
If the variable cost per unit is V and the fixed cost is F, then:
at the 800 level:
800V + F = 16400
at the 1200 level:
1200V + 1.4F = 23600
If you multiply everything in the first equation by 1.4, then:
1120V + 1.4F = 22960
If you subtract everything in the equation from everything in the second equation, then:
80V + 0 = 640
Therefore V = 640 / 80 = $8 per unit.
November 20, 2017 at 8:40 am #416825One of the best teacher in this planet thank you very much sir
November 20, 2017 at 8:47 am #416828Sir 1.4 is that 40%
November 20, 2017 at 9:00 am #416836Multiplying by 1.4 is the same as adding on 40%
November 20, 2017 at 9:02 am #416839Thank you very much sir u r the best
November 20, 2017 at 9:13 am #416843Sir i have little confuse what would if in the same question fixed cost is 1100 unit
November 20, 2017 at 7:00 pm #416985But it isn’t, and in this question it couldn’t be!!
Have you watched my lectures on the high low method ?