Sir,
We have already calculated standard cost of labour per hour (i.e. Standard rate).
while at the time of calculating labour rate variance why do we divide actual hours paid by 0.95 instead of multiplying it with 12 directly?Thanks in advance
August 29, 2017 at 7:24 am #403996anyone can post a new thread in this forum?
August 29, 2017 at 7:59 am #404013Dear John, I cannot post anything to this sub forum as well as post my question.
August 29, 2017 at 8:06 am #404024Ema: We don’t divide the hours by 0.95.
The staff have agreed to take a pay cut of 5% and so for every $95 they are actually paid, the standard cost would be $100.
So they are taking the total that was actually paid and dividing that by 0.95 to find out what they would have been paid at standard cost.August 29, 2017 at 8:07 am #404025Harry: If you have a question you want me to answer, then yes – start a new thread in the forum. I don’t know what you mean by ‘sub forum’.