• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

ifrs 15

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › ifrs 15

  • This topic has 1 reply, 2 voices, and was last updated 8 years ago by MikeLittle.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • July 29, 2017 at 7:11 pm #399272
    adarsh1997
    Participant
    • Topics: 646
    • Replies: 282
    • ☆☆☆☆

    Hi Mike!

    I have an issue solving a question in the BPP kit.
    Need your help

    On 1 October 20X2 Pricewell entered into a contract to construct a bridge over a river. The total contract revenue was $50 million and construction is expected to be completed on 30 September 20X4.
    Costs to date are:
    $m
    Materials, labour and overheads: 12
    Specialist plant acquired 1 October 20X2: 8
    The sales value of the work done at 31 March 20X3 has been agreed at $22 million and the estimated cost to complete (excluding plant depreciation) is $10 million. The specialist plant will have no residual value at the end of the contract and should be depreciated on a monthly basis. Pricewell recognises satisfaction of performance obligations on the percentage of completion basis as determined by the agreed work to date
    compared to the total contract price.
    What is the profit to date on the contract at 31 March 20X3?

    1.The answer is $8,800,000.
    2. How do we deal with the $8M specialist cost? Do we include the whole $8M or the depreciation as cost?

    Thanks.

    July 29, 2017 at 9:15 pm #399359
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23329
    • ☆☆☆☆☆

    Contract value is $50m

    Costs to date $12m
    Costs to complete $10m
    Specialist machinery cost $8m

    Total cost $30m

    Anticipated profits $20m

    Contract is 44% complete ($22m as a percentage of $50m ie Pricewell recognises satisfaction of performance obligations on the percentage of completion basis as determined by the agreed work to date compared to the total contract price)

    44% x $20,000,000 anticipated profit = $8,800,000

    OK?

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • The topic ‘ifrs 15’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Abdjr11 on The cost of capital – The cost of equity – ACCA Financial Management (FM)
  • Durrani118 on Using Information Systems – ACCA Performance Management (PM)
  • Sejinpeter on MA Chapter 1 Questions Accounting for Management
  • ZaidRaza on IAS 16 Accounting for a revaluation – CIMA F1 Financial Reporting
  • mrjonbain on Chapter 11 Capital Gains Tax – Individuals TX-UK FA2023

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in