Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › Revenue
- This topic has 1 reply, 2 voices, and was last updated 8 years ago by
MikeLittle.
- AuthorPosts
- May 27, 2017 at 5:55 pm #388429
Hi My dear Tutor. I have a question relating to the below question
Trial balance at 31 march 2017
on 1 October 2013 Pricewell entered into a contract to construct a bridge over a river. The
agreed price of the bridge is $50 million and construction was expected to be completed on 30
September 2015. The $14•3 million in the trial balance is:materials, labour and overheads 12,000
specialist plant acquired 1 October 2013 8,000
payment from customer (5,700)
––––––
14,300
The sales value of the work done at 31 March 2014 has been agreed at $22 million and the estimated cost to complete (excluding plant depreciation) is $10 million. The specialist plant will have no residual value at the end of the contract and should be depreciated on a monthly basis. Pricewell recognises profits on uncompleted contracts on the percentage of completion basis as determined by the agreed work to date compared to the total contract priceSolution
cost to 31 march 20×7
material-12000
depreciation(8000/24*6)-2000
overall-14000estimated cost excluding depreciation-10000
depreciation-6000
16000from 1 october 20×6 to 30 september 20×8 24 month
from 1 october 20×6 to 31 march 20×7-6months-2000
from 31 march 20×7 to 30 september 20×8-18mosths-6000percentage complete 22000/50000*100%=44%
under p/l
revenue(50000*44%)=22000
cost of sales(16000+14000*44%)-13200
gross profit-8800under SFTP
profit recognised-8800
cash recevived-5700
trade recevivable-17100Sometimes I face instead of trade receivables there is written contract asset.Also trade receivable and Work in progress together creates contract asset such as contract assett =work in progress +trade receivable
this part slightly unclear for me could you explain it on this example?
WHat is work in progress?May 28, 2017 at 9:02 am #388512“Sometimes I face instead of trade receivables there is written contract asset”
I don’t believe that I’ve ever seen that! Amounts doe from customers by way of un-billed work in progress? Yes
Amounts due from customers by way of amounts invoiced less amounts received? Yes
But “written contract asset”? No
I suggest that you work through the examples in the course notes where the calculations for the two figures for “Amounts due from customers” are clearly shown
In addition, if you check the “REvision questions” on the F7 home page, you’ll see that I have recorded my own answer to Pricewell and that should be easily followable
OK?
- AuthorPosts
- The topic ‘Revenue’ is closed to new replies.