Sir, In Kaplan book, there is a line said “Projects should be accepted if IRR is greater than the cost of capital “.Could you please tell me what does it mean.
I understand the IRR as the discount rate that, if applied to the cash flows if a project, would produce a net present value of zero. If the IRR was less than the cost of capital, then it wouldn’t be worth pursuing with the project.