Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Tramont co, pilot paper qu 1
- This topic has 7 replies, 4 voices, and was last updated 8 years ago by John Moffat.
- AuthorPosts
- May 6, 2015 at 10:20 am #244313
Dear john,
hope you are fine. In tramont for the US cflows there is a contribution per unit of 4 on each unit sold in the foreign country…well one thg that is not clear, it says somewhere sellg price is not subject to inflation and only cost in respective inflation rates are subject..i get that but why did they inflate that contribution /unit of $4 ..please clarify me on that..when i worked i didnt do it because i didnt see any place of contribution suject to inflation ratesMay 6, 2015 at 2:58 pm #244354It is an assumption (and the examiner should really has stated it as one of his assumptions).
However, there is a logic to the assumption. Most companies would wish to increase their selling prices as their costs increased, but it is not always possible (because of competition etc..) So certainly in Gamala they are not increasing the SP (because the question says so). However Tramont selling to Gamala is a bit different because they can happily put up their price 🙂
Again, though, it is an assumption.May 8, 2015 at 4:36 am #244737thxx John..:)
May 8, 2015 at 9:12 am #244758You are welcome 🙂
May 16, 2015 at 6:53 am #246274Hi Sir,
Regarding part a I do not understand that how the additional contribution figures are calculated for year 1-4 as it is given in working 7 .
Thanks in advanceMay 16, 2015 at 8:27 am #246303Just over half way down the first page of the question, it says that Tramont is supplying a component to Gamala that gives them a contribution of $4 per unit. We know the number of units a year, we know the rate of inflation, and we take 70% of the total to account for the tax at 30%.
June 7, 2016 at 6:04 pm #320487why he is adding 0.4 even though project is financed by equity plus debt
June 8, 2016 at 7:53 am #320699The question says that you should discount at an appropriate all-equity rate (i.e. he wants an APV approach).
The cost of equity if all equity is determined by the asset beta of the project. The question says that this is 0.4 more than the current all equity financed beta.
- AuthorPosts
- You must be logged in to reply to this topic.