Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › June 2008 Neptune
- This topic has 10 replies, 5 voices, and was last updated 7 years ago by John Moffat.
- AuthorPosts
- November 22, 2014 at 3:25 pm #212218
Hi sir,
Can i know how to derive the written down value of 31…?
thanks…
November 22, 2014 at 6:56 pm #212265Cap value 800
Year
0 – first yr allowance (50%) = 400
1 – reducing balance (40%) = 160
2 – reducing balance (40%) = 96
3 – reducing balance (40%) = 57.6
4 – reducing balance (40%) = 34.56
5 – reducing balance (40%) = 20.7total cap allowance = 769
cost 800 – cap all 769 = written down value 31 π
or u can wait for tutor reply for better understanding.
November 23, 2014 at 10:30 am #212337muneebnawaz is perfectly correct π
November 23, 2014 at 10:59 am #212354Hi all,
For the profit on sale of equipment, shouldn’t it be a 9 (40-31)…?
thanks…~
November 23, 2014 at 11:34 am #212377It is! The profit itself is not a cash flow and so we are not interested.
There will be a tax balancing charge on the 9 (and there is in the answer).
November 23, 2014 at 4:00 pm #212456Hi all,
In which part of the question did it mentioned that the PPE will be sold at the end of the project life…?
Thanks…~
November 23, 2014 at 8:15 pm #212490It says it has a residual value of 40. (And it was you who mentioned it in your question when you asked about the profit!!!)
November 26, 2014 at 8:32 pm #213561I have a question there.Why is the 50% allowance done in year 0(2008)? Why not year 1(2009)?
November 27, 2014 at 6:29 am #213652Th examiner is wrong here.
The first allowance would be calculated at the end of the first year (30 June 2009 – time 1), but because he said in the question that the tax timing is 12 months after it arises, then the first capital allowance saving should be on 30 June 2010 (time 2).
July 19, 2017 at 7:25 pm #397642Sir, why indirect costs are not considered in the Npv calcualtion? Cant indirect costs be relevant? and Why answer didnt take inflation into account?
July 20, 2017 at 7:28 am #397705Indirect costs/overheads are only relevant if they change as a result of doing the project. Since they are activity based, part of the total has been allocated to the project for profit purposes, but there is no suggestion that the overall total has changed. The fact that the total inflates is of no relevance, for the same reason.
- AuthorPosts
- The topic ‘June 2008 Neptune’ is closed to new replies.