Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Global Pilot paper – for exams up to December 2012
- This topic has 6 replies, 2 voices, and was last updated 11 years ago by John Moffat.
- AuthorPosts
- September 24, 2013 at 2:20 am #141111
With regard to the GLOBAL PILOT PAPER – FOR EXAMS UP TO DECEMBER 2012
How to calculate the Question 2 (b) (ii) ? There is no explanation for the answers provided (i.e. number of contracts, cost of hedge and as percentage of value).September 24, 2013 at 6:04 pm #141194Although I will tell you how the number of contracts has been arrived at, the Grabbe variant was removed from the syllabus and cannot now be examined.
The only option pricing that can be examined relates to share options.However, the point is that as the exchange rate changes, so too will the price of options, but the option price will change by N(d1) x the change in the exchange rate.
So…using the 3 month transaction for example ……to make the changes cancel out, the number of options we need to deal in is the amount of the transaction (75M) divided by N(d1) (0.5386).
75M / 0.5386 = 278499814 options.
However we can only deal in contracts of 100,000 options and so the number is 2785(The logic is exactly the same as delta hedges when we have share options. As I wrote above, share options can be examined, but the pricing of currency options is no longer in the syllabus)
November 26, 2013 at 7:17 am #147839Thank you sir =] I noted pricing of currency options will no longer be examined.
Anyway, with regard to the same question, could you explain how the figures on “cost of hedge” and ” as percentage of value” arrived? (I am sorry, I have spent long time but still could not figure it out…)
Please do not mind I ask another question in here:
With regard to same past paper – question 3, the answer provided by ACCA:
b (i) “This suggest that this project has a 97.3 per cent probability…….” , may I know how is it computed?\
Many thanks!
November 26, 2013 at 10:03 am #147865In the answer to (b) the cost of a call option has been calculated as 3.1581 pence. They are buying 2785 contracts of 100,000, and so the total cost is 2785 x 100,000 x 0.031581 = 8795309. (The answer is a few 100 different because the examiner has rounded in one place and not in the other!!)
The percentage of value he has taken the total cost of the options divided by the 150M that is at risk.
For question 3, he has looked up in the normal distribution tables for 1.92, and then added 0.5 to the figure. The logic being that there is a 0.473 probability of being that many standard deviations below the average, but because the distribution is symmetrical there is a 0.5 probability of being above the average. So in total, a 0.973 probability of being above the figure.
November 26, 2013 at 10:37 am #147878Sorry sir, I think I was editing my question while you replying. It caused some problem in the reply threads…….
I have another thing to ask for the same question.
b (iii): how to compute the “weighted years” in the table?
Many thanks!
November 26, 2013 at 10:39 am #147881Thank you sir =]
November 26, 2013 at 10:53 am #147885Multiply the year by the duration of the recovery phase
- AuthorPosts
- You must be logged in to reply to this topic.