• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

construction contracts

Forums › ACCA Forums › ACCA FR Financial Reporting Forums › construction contracts

  • This topic has 3 replies, 3 voices, and was last updated 12 years ago by biggles.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • April 15, 2013 at 4:51 pm #122549
    densdumbo1
    Participant
    • Topics: 19
    • Replies: 14
    • ☆

    in the statement of prft n loss….we calculate revenue – cost by multiplying each wid % of completion =gross prft…in this d cost we take is cost to date + cost to complete ryt….but i hav seen in some sums where they hav taken only d cost to date n * wid % of completion….cost to complete in nt taken…y is it ?

    n also in some sums…they find d cost as a balancin fig…
    revenue * %
    – cost (bal fig)
    —————-
    prft * %

    in dis fig of cost sometimes doesnt match when i multiply % of completion * (cost to date+cost to complete)…why is it ?

    April 20, 2013 at 4:06 pm #123020
    densdumbo1
    Participant
    • Topics: 19
    • Replies: 14
    • ☆

    pls help..

    April 20, 2013 at 5:14 pm #123023
    Anonymous
    Inactive
    • Topics: 0
    • Replies: 5
    • ☆

    its been doing a number on me too…..read the ACCA article on their website you will understand abit

    April 29, 2013 at 6:58 am #123828
    biggles
    Participant
    • Topics: 6
    • Replies: 80
    • ☆☆

    Your second problem is probably because in the OT lectures there is one question where a loss is forecast. In that question, the costs to be recognised is a balancing figure.

    I don’t know why in your first question you say there are some questions where “Costs to complete” are not included ….unless it’s because the contract is in its early stages and is not sufficiently progressed to ( I’m quoting Mike! ) “be able to predict with reasonable certainty the ultimate outcome of the project”!!!!

    In that situation, we need to calculate revenue in the usual way and then recognise costs as the same figure as revenue so that no profit is recognised

    I think!

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • Shabi on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • Ark1 on Variance Analysis (part 4) – ACCA Management Accounting (MA)
  • EricObi on IAS 37 – Best estimate – ACCA Financial Reporting (FR)