Hi Sir,
This question came up in the Kaplan Revision Kit and I can’t figure out to solve it.
Question: Budgeted production in a factory for next period is 4800 units. Each unit requires five labour hours to make, Labour is paid $10 per hour. Idle time represents 20% of the total labour time. What is the budgeted total labour cost for the next period?
Since the time worked it 80% of the time paid for (because of the idle time), each unit produced means paying for 5 / 80% = 6.25 hours at $10 per hour.