Instances in which to use ABCForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Instances in which to use ABCThis topic has 1 reply, 2 voices, and was last updated 8 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total) AuthorPosts May 1, 2015 at 9:00 am #243482 RaveenMemberTopics: 25Replies: 25☆☆could you please state the other occasions in which abc costing is more appropriate, other than situations in which cost drivers could be identified May 1, 2015 at 6:01 pm #243546 John MoffatKeymasterTopics: 56Replies: 53816☆☆☆☆☆ABC is always more appropriate when more than one product is being produced!It might not be possible to identify cost drivers for all overheads, but it is always worth attempting to.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In