Hi,
Re the above question – could someone elaborate as to how to arrive at the profit levels noted for various demand levels / contract sizes?
I simply can’t get close – eg Demand Level 400 – Contact Size 300 – answer is $2900 profit?
Are we assuming production at 1200? (which would result in heavy losses from producing additional units for 400 demand)
Or are we assuming JIT style production? Therefore 300 demanded under contract @ $3pu contribution ($9-$6) = $900 minus cost of 100 extra produced? (100x$6=$600) Total profit = £300
or are we assuming additional 100 units can be sold outside of contract therefore additional contribution of $5($11-$6) still only gets total profit of $1400?
I can’t get profit levels anywhere near those quoted in the answers….?
Help!
Regards
Andy
September 9, 2016 at 6:25 pm #339490Hi,
Thanks for your question.This exercise is fully explained during the P2 lecture on expected values- link is below:
https://opentuition.com/cima/cima-p2/cima-p2-risk-uncertainty-expected-values/
Part c is continued on the next video:
https://opentuition.com/cima/cima-p2/cima-p2-risk-uncertainty-perfect-knowledge/Please let me know if these videos do not address your question and Ill get back to you asap.