Morning John Moffat,
I'm stuck on the following question and need your help please.
The following information is available regarding fixed overhead costs and output of 2 production Depts (S&T) of a firm.
Dept S
Allocated / Apportioned Fixed Overhead $60,000
Total Cost of direct materials used $120,000 (I think its Dept Mat Cost)
Total productive labour hours 5,000 hrs
Dept T
Allocated / Apportioned Fixed Overhead $100,000
Total Cost of direct materials used $100,000 (I think its Dept Mat Cost)
Total productive labour hours 10,000 hrs
A product has the following variable cost
Materials
Dept S 3kg @ $4 per kg $12
Dept T 2kg @ $4 per kg $ 8
Labour
Dept S 0.5hrs @ $10 per hr $5
Dept T 1.5hrs @ $10 per hr $15
Variable overheads
1hr @ $5 per hr $5
_________
Total: $45
What is the fixed overhead cost per unit if fixed overheads are absorbed on the basis of departmental material cost ?
My answer:
OAR = Budgeted Overhead / Budgeted Activity
OAR here = Fixed Overheads / basis of departmental material cost
Departmental OAR - Dept S
$60,000 / $120,000 = $0.5
Departmental OAR - Dept T
$100,000 / $100,000 = $1
Dept S
$12 * $0.5 = $6
Dept T
$8 * $1 = $8
Total = ($6+$8) = $14
Could you please tell me whether I am correct in my approach to answering this question.
Every question I have previously encountered has fixed overheads absorbed by reference to labour hours, not dept material cost.
Thanks.
Absorption Costing - OAR- Departmental Rates
Yes - it is correct.
(But why are you attempting questions for which you do not have an answer? You should be using a Revision Kit from one of the ACCA approved publishers - they have answers and explanations to all the questions.)
Thank you for your help John. The question has not been taken from a Revision Kit.
I felt it wise to practice as many F2 questions as possible, taken from a variety of sources.
You are welcome, but again, wherever you find questions it is only really helpful for you if you attempt ones that also have answers!!!
I still don understand. Can u provide more details.thank u
You do not say what details you need. I presume that you have watched our free lectures on this and that you do have the book containing the question and answer?
In the Revision Kit,it is 60*(12/120)+100*(8/100)?14,I want to know what this algebraic expression means?Thank you.
There is no algebra in the expression!!
You do not say which Revision Kit or which question in it.
hello, i still didn't understand why the candidate used a cost to calculate the OAR instead of the budgeted time, could you please elaborate on this, thanks in advance.
You absorb on whatever basis you are told to in the question. In this case it said to absorb on the basis of the material cost.

