LeeShea saysFebruary 8, 2024 at 9:09 pmI worked out the efficiency variance differently. Std efficiency is 48k units to 2k dispatches given you 24u to 1D 2200 d you would expect 52,800 U. Actual units of 50,400 – 52,800 gives you 2400 less units 2400U x $2.50 gives you a $6000 (A)Log in to Reply
LeeShea says
I worked out the efficiency variance differently.
Std efficiency is 48k units to 2k dispatches given you 24u to 1D
2200 d you would expect 52,800 U.
Actual units of 50,400 – 52,800 gives you 2400 less units
2400U x $2.50 gives you a $6000 (A)