cima-p1Activity Based Costing Variances - CIMA P1CIMA P1 lectures Download P1 notes YouTube videoPlay video1 CommentLLee·2y agoI worked out the efficiency variance differently. Std efficiency is 48k units to 2k dispatches given you 24u to 1D 2200 d you would expect 52,800 U. Actual units of 50,400 - 52,800 gives you 2400 less units 2400U x $2.50 gives you a $6000 (A)Leave a commentPost comment
Std efficiency is 48k units to 2k dispatches given you 24u to 1D
2200 d you would expect 52,800 U.
Actual units of 50,400 - 52,800 gives you 2400 less units
2400U x $2.50 gives you a $6000 (A)