• Skip to primary navigation
  • Skip to main content
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA PM:
  • PM Notes
  • PM Lectures
  • Practice Questions
  • PM Flashcards
  • Revision Lectures
  • PM Mock Exam
  • PM Forums
  • Ask the Tutor
  • Ask AI (New!)

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Types of budget – ACCA Performance Management (PM)

VIVA

Reader Interactions

Comments

  1. gift says

    April 30, 2023 at 8:26 pm

    Thank you for the clear and concise lectures Mr. Moffat, just been thinking, is there a difference in meaning between the principal budget factor and limiting factor covered under decision making techniques.

    Log in to Reply
  2. Hilal380 says

    January 4, 2023 at 8:05 am

    Hi John, some types of budgets which are part of syllabus are missing in notes and lecture.
    Activity based budget, feed forward budgets and there are some other stuff in acca approved text books which are missing in your notes.
    these things are worrying me.
    btw thanks for the free lecture and notes.

    Log in to Reply
    • John Moffat says

      January 4, 2023 at 4:26 pm

      Activity based budgeting only requires knowledge of activity based costing, and in the exam is relevant to control (i.e. variances). ABC variances are explained in my lectures.

      Feed-forward control again relates to variance analysis and is explained in the variance lectures.

      Log in to Reply
      • Hilal380 says

        January 5, 2023 at 1:39 pm

        Thanks John. No worries now.

      • John Moffat says

        January 5, 2023 at 5:45 pm

        You are welcome 馃檪

  3. Jina99 says

    May 6, 2022 at 6:30 pm

    Thanks for the video! When you prepared the flex budget example, your showed the budget as revenue, variable costs, contribution, fixed overheads and profit. In the exam, would it require to be presented as such or can it also simply be presented as revenue minus all costs equals profit? Thanks again.

    Log in to Reply
    • John Moffat says

      May 7, 2022 at 9:01 am

      It depends on what the question asks for. If it just wants the profit then it doesn’t matter how you arrive at it.

      Log in to Reply
      • Jina99 says

        May 9, 2022 at 6:50 pm

        Thank you!

  4. lwhnatalie says

    April 13, 2022 at 10:28 am

    Sir, the answer to example 2 (Chapter 11) “statement” part is not covered. The statement is summarised for management but what is the statement referring to?? Is it refer to the actual activity level column?? I don’t understand the presentation of this statement even though the actual profit $7500 is the same as the columnar form of actual profit.

    Thank you

    Log in to Reply
    • John Moffat says

      April 13, 2022 at 2:22 pm

      The statement is explaining why the actual profit is different from the budgeted profit.

      Log in to Reply
      • lwhnatalie says

        April 14, 2022 at 1:35 am

        Do you mean the budgeted profit is relates to original budgeted profit? But the variance for variable cost was the difference between flexed and actual, still a bit confusing.

      • John Moffat says

        April 14, 2022 at 7:19 am

        We compare the actual costs with the flexed costs to see if the manager responsible for the particular cost was paying the right price per. unit or not. If they were paying too much per unit then we need to find out why.

        However this lecture was primarily about flexing the budgets. The variances are discussed in detail (with much more arithmetic involved) in the later chapters specifically on variance analysis.

  5. hermela says

    March 13, 2022 at 2:24 pm

    hello sir it is really good lecture but i cant get the concept of rolling budget

    Log in to Reply
    • John Moffat says

      March 13, 2022 at 4:43 pm

      You will have to say which part of the example I give in the lecture is puzzling you, and then I will try and explain more 馃檪

      Log in to Reply
  6. ajiemirates@gmail.com says

    July 9, 2021 at 5:01 pm

    Hi John,

    Thanks for your excellent lectures, i am confused on the below question available on practice question. Is the below statement are correct.

    Question – Rolling budgets are always prepared for the following 12 months period.

    from my understanding i answered as correct, but it was incorrect. bit confused could you please explain why its incorrect.

    Log in to Reply
    • John Moffat says

      July 10, 2021 at 9:29 am

      I would really need to see the whole question. However it is probably because although rolling budgets are normally for 12 month periods, that is not a rule – they could be done (for example) for six month periods.

      Log in to Reply
  7. shakir7385 says

    May 7, 2021 at 11:20 am

    Dear John, in an environment where rolling budget is practiced, the sole purpose of this budget comes to my mind is only to check the performance on monthly basis and revised subsequent period budget. So if the purpose is to have a check and revision of budget each month so why consideration is given to 11+1 months? why not just 2 to 3 subsequent months only?

    Log in to Reply
    • John Moffat says

      May 7, 2021 at 2:13 pm

      The purpose of the budget is to be able to forecast for the coming 12 months so as to help with planning for the future.

      Log in to Reply
  8. Lslaizer says

    April 10, 2021 at 2:28 pm

    Thanks John. Indeed it’s a good lecture.
    One issue is the timing when explaining rolling budget dec 07: jan 08 -feb 08.. I was expecting this to be a one year duration as presented in subsequent period. Thnks

    Log in to Reply
  9. m900 says

    February 6, 2021 at 4:33 pm

    i remember you teaching the concept of flexed budget in f2. good revision. Thank you as always ?

    Log in to Reply
    • John Moffat says

      February 6, 2021 at 5:06 pm

      You are welcome 馃檪

      Log in to Reply
  10. maumau says

    April 21, 2020 at 12:50 pm

    Hi sir, I don’t understand how you actually calculate the flexed budget and also on how you arrived at $5 for revenue, 2.5 for labour and 1.5 for overhead. I would’t mind also if you explain why flexed budget is needed and it usefulness.

    Log in to Reply
    • John Moffat says

      April 21, 2020 at 3:31 pm

      The purpose of the flexed budget is so we can compare what actually happened with what should have happened for the actual level of activity. I do explain this in the lecture and expand on it in the following lectures on variance analysis.

      As far as the revenue and the variable costs are concerned, the budgeted revenue was 100,000 for sales of 10,000 units and therefore the revenue should be 100,000/10,000 = $10 per unit. It is the same logic for the variable costs.

      Log in to Reply
  11. avrondavids25 says

    May 17, 2019 at 7:42 pm

    Dear Sir,
    I trust you are well.
    How did you calculate the contribution of 12500 and 18500?
    Many thanks

    Log in to Reply
    • avrondavids25 says

      May 17, 2019 at 7:44 pm

      Sorry, I understand now.

      Log in to Reply
  12. khussaini says

    November 23, 2018 at 1:51 pm

    Hi. In case of a service industry, flexed budgeting is possible?

    Log in to Reply
    • John Moffat says

      November 23, 2018 at 2:33 pm

      Yes, but then you would flex on the number of services – not obviously on the number of units produced.

      Log in to Reply
  13. leobenny says

    November 9, 2018 at 10:58 am

    Sir is ABB- activity based budgeting important ??
    Just asking because you didn鈥檛 talk about it in the lectures..

    Log in to Reply
    • John Moffat says

      November 23, 2018 at 2:33 pm

      Less important (and certainly not for calculations).

      Log in to Reply
  14. alie2018 says

    November 5, 2018 at 9:44 am

    Thanks John. The flexed budget prepared at the end of the budget period and is based on the actual level of activity using the original standard price and cost. The difference between the flexed budget and actual result is the variance.

    Log in to Reply

Leave a Reply Cancel reply

You must be logged in to post a comment.

Copyright © 2025 路 Support 路 Contact 路 Advertising 路 OpenLicense 路 About 路 Sitemap 路 Comments 路 Log in