• Skip to primary navigation
  • Skip to main content
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA PM:
  • PM Notes
  • PM Lectures
  • Practice Questions
  • PM Flashcards
  • Revision Lectures
  • PM Mock Exam
  • PM Forums
  • Ask the Tutor
  • Ask AI (New!)

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Short-term Decision making – Relevant Costing – ACCA Performance Management (PM)

VIVA

Reader Interactions

Comments

  1. pkarki says

    May 12, 2021 at 6:43 am

    thank you professor you are a real master.
    i enjoy your enthusiasm and conceptual understanding for mathematical problems.

    Log in to Reply
    • John Moffat says

      May 12, 2021 at 7:52 am

      Thank you for your comment 馃檪

      Log in to Reply
  2. shakir7385 says

    April 26, 2021 at 7:59 pm

    Dear John,
    In Example 2, while calculating the relevant cost of point 4 (i.e. Machine maintenance cost). What if due to inclusion of new work, the company change its depreciation policy and say if it was to be depreciated previously over a period of 40 years, after inclusion of new product line company start to depreciate its relevant class of asset over a period of 30 years which results in more depreciation charge on monthly basis. Would that additional charge on monthly basis be treated as the additional cost due to addition of new product line, and the same shall be considered as additional cost?

    In Example 5, as you mentioned that losing contribution of $2 due to inclusion of new production will only be considered if the new production gives at-least $2 or more contribution. Since we do not have details available about the contribution of new production so why we considered the taking off existing job of 2000 units?

    In Example 6, why we are treating purchase cost of 7,500 kg material as a sunk cost despite that we have option available to recover this amount at $4.20 per kg.? Shouldn鈥檛 the difference of purchase price of that material (which is although not given in question) and the recoverable amount is treated as sunk cost?

    Thanks in advance for your precious time!

    Log in to Reply
    • John Moffat says

      April 27, 2021 at 8:21 am

      The machine will be depreciated whether or not we do the on-off contract. There is no extra cost involved if we do the contract.

      If we do the contract then 2,000 hours will be taken away from the existing job. Therefore we will lose the contribution that could be earned and this is therefore effectively a cost of doing the new contract. It is irrelevant what contribution we earn from the new contract. We are calculated the total cost to the company of doing the new contract. It is only when we know what it will cost us to do that we can decide how much we need to charge to do it.

      The materials have already been bought and the money has been spent whether or not we do the new contract. The original cost is therefore irrelevant. All that is relevant is that if we do the new contract we will then not be able to sell the inventory and so doing the contract will lose us the $4.20 that we would otherwise receive.

      Log in to Reply
  3. LiyaJaison says

    February 26, 2021 at 9:16 pm

    Hy Sir,
    Could you please explain me materials (note 6) the wording of amounting to 10,000 that is given in the bracket. What does that mean?

    Also when I checked to the answers at the end of notes it is given historic cost of 34000 (for note 6) what is this amount referred to?

    Log in to Reply
    • John Moffat says

      February 27, 2021 at 8:15 am

      The question says that there are 10,000kg in inventory. The special order needs 7,500 kg of materials and so these will come from the inventory (since they are not wanted for anything else). The question also says that the $34,000 appearing in the original schedule was the cost when the kgs were first purchased.
      Have you watched the lecture working through this example?

      Log in to Reply
      • LiyaJaison says

        February 27, 2021 at 3:48 pm

        Thank you Sir for the reply.
        Yes sir, I watch lectures. And also do the mcq questions at the end.

  4. evisevi says

    February 11, 2021 at 11:29 pm

    Dear John,
    I am not very clear on committed cost and why do we not include it in relevant costing. Can you please give me an example of committed cost?
    For example, is a solicitor’s cost committed cost? It is usually paid wether or not the deal goes through. As it is relevant to the project itself, I would think of it as a relevant cost.
    Many thanks!

    Log in to Reply
    • John Moffat says

      February 12, 2021 at 6:46 am

      A committed cost is a cost that will have to paid whether or not the new contract is accepted. We are not doing financial accounts, to make the decision we simply need to know whether or not accepting a new contract means paying extra costs or not. In your example of a solicitor, you would only pay the costs if you decided to go ahead with using a solicitor (whether or not the deal goes through is irrelevant, so it is not a committed cost).

      Log in to Reply
      • evisevi says

        February 13, 2021 at 10:30 am

        Many thanks!

  5. japime says

    November 2, 2020 at 9:22 pm

    Hello sir!

    In the bank overdraft of $20 000, you had a reply wherein you said that it would be paid back in the future. Therefore, is it safe to say that it is a committed cost since we will pay it back whether or not we take the special order?

    Log in to Reply
    • John Moffat says

      November 3, 2020 at 9:48 am

      Effectively yes (although what we call it doesn’t actually matter) 馃檪

      Log in to Reply
  6. salminawaris says

    August 14, 2020 at 1:32 pm

    You are a an amazing teacher.Bless you Sir!

    Log in to Reply
    • John Moffat says

      August 14, 2020 at 3:15 pm

      Thank you for your comment 馃檪

      Log in to Reply
  7. 7fsa says

    June 28, 2020 at 5:17 pm

    Dear John, thank you so much for your appreciated time.

    Log in to Reply
  8. kigongo says

    March 31, 2020 at 11:19 pm

    Thank you!

    Log in to Reply
    • John Moffat says

      April 1, 2020 at 8:54 am

      You are welcome 馃檪

      Log in to Reply
  9. rosicm says

    February 5, 2020 at 9:36 pm

    Hi John,

    i saw someone asked this already, but still not sure why you calculate it that way then. So if I use machine 4000hrs extra and add lost contribution, I calculate it as 4000×3 + 2000×2 = 16000 or 6000×3 + 2000*(2-3), where 2-3 represents lost contr. minus saved machine OH, in both cases you get 16k relevant costs. What am I forgetting here so I would get to 22k like you did?

    Thanks for assistance in advance, much appreciated.

    Log in to Reply
    • John Moffat says

      February 6, 2020 at 7:52 am

      For the 2,000 hours being used on an existing job, the $2 contribution is after charging variable costs and so is after charging the running costs of $3. They will still be paying the running costs for those 2,000 hours, so what they will actually be losing is $5 per hour (the revenue less other variable costs).
      So in total they are losing 2,000 x $5 = $10,000. In addition they are paying for another 4,000 hours at $3 per hour, which is $12,000. So a total of $22,000 馃檪

      Log in to Reply
      • rosicm says

        February 6, 2020 at 5:18 pm

        Perfect, thanks a lot for clarifying this issue.

        Best, Miha

      • John Moffat says

        February 7, 2020 at 7:45 am

        You are welcome 馃檪

  10. lambujon99 says

    December 6, 2019 at 1:41 pm

    Hi sir, I’d like to clarify:
    “Because the business does not have adequate funds to finance the special order, a bank overdraft amounting to $20,000 would be required for the project duration of three months.” Does this not mean that they spent specifically 20,000 more to finance the special order, therefore, is considered an opportunity cost?

    Log in to Reply
    • John Moffat says

      December 6, 2019 at 1:56 pm

      No. There is no mention of them having to spend the $20,000 on anything specific. So presumably they will pay back the $20,000 later and the only relevant cost is the interest.

      (This is in fact a very old exam question)

      Log in to Reply
  11. yulia150391 says

    August 17, 2019 at 7:05 pm

    Hi,

    Thank you very much John. I am so sorry but I did not understand in the example 2, in the note 3, why do we ignore general overheads of $3,000. Could you please explain one more time here.

    Many thanks in advance

    Log in to Reply
    • azbalogun says

      December 4, 2019 at 1:00 am

      As explained, the overhead apportionment of $3000 would be incurred whether or not the special order is made. However, the incremental cost of $1000 is an extra cost resulting directly as a result of the engagement of the new special order which is a relevant cost. I hope this helps

      Log in to Reply
  12. nodirjon says

    July 31, 2019 at 10:47 pm

    Good day sir,

    I think, I misunderstood #2 of example 2: In the notes it says “In addition, the supervisor would lose incentive payments in his normal work amounting to $2,500.” From that sentence, doesn’t it mean that the supervisor would lose incentive during normal work and that is why in the special order work he/she is gets the incentive?

    Thank you in advance for your clarification!

    Log in to Reply
    • John Moffat says

      August 1, 2019 at 7:47 am

      The company will not pay him the normal bonus (of $2,500) and so the company will save $2,500), but instead they will pay him $3,500 and so the net cost to the company will be an extra $1,000.

      Log in to Reply
  13. levanrich says

    April 18, 2019 at 3:08 am

    Good day,
    #5 of example 2. If you have available capacity of 4000 hrs and the special order needs 6000 hr. shouldn’t the cost be 2000hr @$3 per hr (needed to make up that 6000 hr) plus the opportunity cost of taking that 2000hr off their normal job? Because there is no extra cost involved for that 4000 hrs if the machine has the capacity.

    Log in to Reply
    • John Moffat says

      April 18, 2019 at 6:02 am

      Although the machine is capable of running for an extra 4,000 hours, it is not currently doing so (which is why there is available capacity). If it does run for the extra 4,000 hours then there will be extra running costs (such as more electricity used).

      Log in to Reply
      • tugcem says

        September 29, 2019 at 8:01 pm

        Hi John
        Thanks for the lecture again.
        Relating this question, if it wasn’t the machine and it was labour that has spare capacity, do we still pay extra? We already pay them anyways yes?

      • John Moffat says

        September 30, 2019 at 7:55 am

        It depends on the wording. If labour is paid a fixed salary then there is no extra cost. If labour is paid by the hour then there will be extra cost.

      • vidhi05255 says

        August 9, 2020 at 5:06 pm

        Hello Mr John,
        I have question for point 5
        4000hrs is available capacity which means machine is anyways idle for 4000hrs and hence idle capacity hours relevant cost is 0.
        For 2000 hrs *5 = 10000 shall be relevant cost??

  14. alie2018 says

    October 31, 2018 at 8:44 am

    Thanks John. Excellent presentation. Only future incremental cash flows should be considered as relevant in undertaking the special order. It is economical to hire cheaper subcontractors for the special order than higher cost might suggest. Fixed cost is not relevant unless there is an incremental fixed cost or a directly attributable fixed cost (product specific fixed cost). Apportioned costs are not relevant. Opportunity cost is always relevant (value of the best alternative foregone for the special order).

    Depreciation is not a cash flow so not relevant. Sunk (dead) cost in respect of materials is never relevant (we can’t change the past).

    Log in to Reply
  15. hitsui says

    October 28, 2018 at 2:12 pm

    Hello,
    could you please explain why we are not using the replacement cost instead of the disposal cost of ($4.20)?

    Because material is no longer used, but it is used for the special contract.
    So i thought that we would use the materials at cost $33.375 and the remaining materials will be sold off.

    Im just confused and can’t understand unless this isnt cleared, please.

    Log in to Reply
    • John Moffat says

      October 28, 2018 at 2:54 pm

      They could do what you suggest, but they would then be paying out 33,375 to buy new materials and would only be receiving 31,500 by selling the existing materials.

      It would therefore be cheaper to not buy new materials and simply use the existing materials.

      Log in to Reply
  16. saiteja says

    October 28, 2018 at 2:04 pm

    Hi John ,

    In the bank overdraft part of the question , I have considered a different scenario where the company has adequate funds yet decides to take a loan amounting to $20,000 specifically dedicated for the one-off job and would be repaid after the same 3 month duration and for example this was done to allocate the existing companies funds to expenses without going negative in the bank balance. Will the $20,000 loan for the specific job be considered as extra costs relevant to the one-off job in this scenario ?

    Thank you very much for the lectures Sir.

    Log in to Reply
    • John Moffat says

      October 28, 2018 at 2:51 pm

      No – the situation would be exactly the same. Just as with the overdraft, the money is repaid (and so not actually spend on the project) and therefore the only cost is the interest.

      Log in to Reply
      • aayushi says

        August 14, 2019 at 3:47 pm

        Sir I am still very confused.
        20,000 is more like a replacement cost, because your going to have to take the bank overdraft because youve used up 20,000 from the amount set aside for the normal course of actions.

      • John Moffat says

        August 15, 2019 at 7:12 am

        The question lists where money is spent and presumably that is the reason they went overdrawn, but there is no mention of specifically spending thee 20,000 on anything. If you borrow 20,000 from me, you will have to repay me and the cost involved of borrowing is just the interest you would have to pay me.

  17. jareerabedin says

    September 24, 2018 at 11:24 am

    Sir, regarding the final point on the overdraft issue, isn’t the bank overdrafting $20,000 because of the special project? Does it not mean that if the special project wasn’t accepted then an overdraft of $20,000 wouldn’t occur? So, Shouldn’t we add $20,000 in addition to the interest payments?

    I’m hoping you can clarify
    Thank you so much

    Log in to Reply
    • John Moffat says

      September 24, 2018 at 4:02 pm

      It is true that the overdraft would not occur (and therefore they would not be paying interest).

      However it does not say that they spent the 20,000. It simply means that their balance balance goes negative for three months (and then presumably it stops being negative at the end of three months).

      Log in to Reply
      • jareerabedin says

        September 24, 2018 at 6:26 pm

        thank you sir

      • John Moffat says

        September 25, 2018 at 6:02 am

        You are welcome 馃檪

  18. jassimalmahal says

    September 23, 2018 at 5:11 pm

    Hi

    why we do not charge the whole 18% interest but only for 3 month , as understood the the OD is taken because of this special order so the whole interest should relevant not only 3 month duration of the job. please clarify my doubt
    thanks

    Log in to Reply
    • John Moffat says

      September 24, 2018 at 7:40 am

      Interest is always given as a yearly rate (unless told differently). Therefore the interest has only been calculated for 3 months.

      Log in to Reply
  19. mhfrdzi says

    September 4, 2018 at 5:13 am

    Sir,
    Can you explain for the materials part as I don’t really quite understand. I will appreciate your help.

    Log in to Reply
  20. tabusheev says

    September 1, 2018 at 4:23 pm

    When you account for machine overheads, why you multiply $3 electricity for 6000 hours, when there are 4000 hours available capacity? If you take 2000 hours of capacity from another process, so you will not spend extra electricity for it.

    Log in to Reply
    • John Moffat says

      September 2, 2018 at 10:11 am

      Correct – we will be paying the electricity anyway. However we will be losing the revenue from the other job and saving all the other variable costs (except for electricity).
      The net loss (revenue less other variable costs) is always the same as the contribution plus the electricity.

      Log in to Reply
Newer Comments »

Leave a Reply Cancel reply

You must be logged in to post a comment.

Copyright © 2025 路 Support 路 Contact 路 Advertising 路 OpenLicense 路 About 路 Sitemap 路 Comments 路 Log in