sir is it wrong to find the bottle neck by calculating the productivity of each process per hour
A B C pressing 2 2 1.5=5.5 stretching 4 1.5 4 =9.5 rolling 1.5 4 4 =9.5
( This the question u did in the video)
So the lowest productivity is in the pressing process. Is the wrong to apply for all the questions sir? cuz this maybe is okay with this question because of the numbers
tpile says
sir is it wrong to find the bottle neck by calculating the productivity of each process per hour
A B C
pressing 2 2 1.5=5.5
stretching 4 1.5 4 =9.5
rolling 1.5 4 4 =9.5
( This the question u did in the video)
So the lowest productivity is in the pressing process.
Is the wrong to apply for all the questions sir? cuz this maybe is okay with this question because of the numbers
tpile says
It’s
2,2,1.5=5.5
4,1.5,4=9.5
1.5,4,4=9.5
Above productivity per hour in order of A,B,C
Sorry if it is unclear
John Moffat says
What you have written is correct 馃檪
tpile says
Thankyou sir
uketui januarius says
Please explain how i can calculate the throughput accounting ratio using bottleneck
John Moffat says
It is calculated in the normal way, but using the time spent in the bottleneck.
accakeisha says
Can you not down the calculations?so I can compare with mine