• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

March 2026 ACCA Exams Results

Comments & Instant poll

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

ADVANCED IDLE TIME VARIANCE

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › ADVANCED IDLE TIME VARIANCE

  • This topic has 1 reply, 2 voices, and was last updated 5 years ago by AvatarJohn Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • March 8, 2021 at 11:26 am #613931
    AvatarABDULLAHI312
    Participant
    • Topics: 106
    • Replies: 97
    • ☆☆☆

    Hi sir
    Example 5 on page 61. 5% of the hours paid for are idle. my concern is when we are making budget, we will work through what we think the budgeted production will cost us. effectively there we will be talking of the hours we will going to pay for. in our budget we have included 400hrs of idle time. why did you computed for standard idle hours of what was paid when our budget was only 400hrs of idle time? i thought we should compare the actual idle hours for actual production to the budgeted idle hours. little bit confused here.
    thanks

    March 8, 2021 at 2:59 pm #613959
    AvatarJohn Moffat
    Keymaster
    • Topics: 57
    • Replies: 54838
    • ☆☆☆☆☆

    Have you watched the lectures working through this chapter?

    For variance analysis we never compare the actual results with the original budget – we flex the budget as I explain in my free lectures on basic variances.

    If they pay for more hours then we would expect there to be more idle hours. The standard idle hours should be 5% of the hours they actually paid for.

    We examine whether or not they worked too many or to few hours when we calculate the efficiency variance.

    (I hope that you are watching the free lectures because it would be a complete waste of time to use the notes without watching the lectures. They are only lecture notes and it is in the lectures that I work through the examples and explain and expand on the notes.)

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • oabilentatiwa on Process Technology and Quality control – CIMA E1
  • Inspire on SWOT Analysis – ACCA Strategic Business Leader (SBL)
  • Casair on Statement of cash flows – Example 1 (revision) – ACCA Financial Reporting (FR)
  • Mellytac on Sales Mix Variance – Variance analysis – ACCA Performance Management (PM)
  • newspring.kr on Group SFP – Example (PUPs) – ACCA Financial Reporting (FR)

Copyright © 2026 · Contact · Advertising · OpenLicense · About · Sitemap · Privacy Policy · Cookie settings · Comments · Log in