sir generally the Working capital is released immediately in the yr the project ends. So in this question i thought that WC will be finally released in yr 5(when the project ends) but somehow they don’t release it until yr 6. Which comes as very strange to me. Can you explain why has the examiner done such mysterious thing, without alluding to such a thing.
I do not why the examiner did that – the examiner has changed twice since this question was asked.
You would have got full marks if you had recovered in the working capital at time 5, and for current exams you should recover it at time 5.