question Mesmermagic co June 2011Forums › ACCA Forums › ACCA AFM Advanced Financial Management Forums › question Mesmermagic co June 2011This topic has 1 reply, 2 voices, and was last updated 7 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts August 8, 2017 at 10:36 am #400973 domwongukMemberTopics: 1Replies: 0☆Hi,Why in the npv of this project is the £7m development cost included in the calulation. Why is it not a sunk cost and therefore should not be included in the NPV of the project?Thanks August 8, 2017 at 4:37 pm #401046 John MoffatKeymasterTopics: 57Replies: 54648☆☆☆☆☆How can it be a sunk cost when the question says “they will spend $7 at the start of each of the next 2 years….”???Sunk costs are when the money has already been spent.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In