It is very similar to an example that I work through in the lecture.
The number of hours that are worked in cost centre X are (8,000 x 3.0) + (8,000 x 2.5) = 44,000 hours. The total overheads in cost centre X are $88,000. Therefore the overheads per hours are 88,000 / 44,000 = $2 per hour.
In a similar way, the overheads in cost centre Y are $4 per hour.
Therefore the total overhead cost of product M is (2.5 hours x $2) + (2.0 hours x $4) = $13 per unit.
Non-production overheads are absorbed at rate of 120% of prime cost: Prime cost= direct material+direct labour= 300+400=700, then 120% of 700 means 840. In general, non-production overheads are absorbed per labour hour or machine hour, etc since what the question specifies for a base. In this example, it mentions, absorption is based on the rate of prime cost, so you need to follow what the question says.
FYI:
Choosing the appropriate absorption base The different bases of absorption are as follows. ? A percentage of direct materials cost ? A percentage of direct labour cost ? A percentage of prime cost ? A rate per machine hour ? A rate per direct labour hour ? A rate per unit ? A percentage of factory cost (for administration overhead) ? A percentage of sales or factory cost (for selling and distribution overhead)
No, the question just wants you to calculate the fixed overheads per unit for product M.
You need to calculate the overhead absorption rate for each of the 2 cost centres as I do in the free lectures, and then you can calculate the fixed overheads for product M.
adheeb says
this lecture is the best I am fully focussing on this lecture rather than my local lecture
John Moffat says
Thank you for your comment 馃檪
JosephPa says
Good day
Why does the actual fixed overheads differ from budgeted fixed overheads?
John Moffat says
Because it is impossible to forecast exactly what will happen in the future.
mannannagpal says
are delivery costs to customers non-production overhead costs?
John Moffat says
Yes
mukambamichael7@gmail.com says
Thank you Sir, got 75% had made a mistake on Q4 but I have rectified it. your lectures are simple and straightforward Thank you.
5327900ALLEN says
Hello, still struggling to understand qn 3. Kindly take me through plz
John Moffat says
It is very similar to an example that I work through in the lecture.
The number of hours that are worked in cost centre X are (8,000 x 3.0) + (8,000 x 2.5) = 44,000 hours.
The total overheads in cost centre X are $88,000.
Therefore the overheads per hours are 88,000 / 44,000 = $2 per hour.
In a similar way, the overheads in cost centre Y are $4 per hour.
Therefore the total overhead cost of product M is (2.5 hours x $2) + (2.0 hours x $4) = $13 per unit.
5327900ALLEN says
Thanks much Sir.
Gat it now
Asif110 says
Hello sir,
If cost centre is also an item of equipment as per Q2, then what is the difference between an item of cost unit and an item of cost centre ?
John Moffat says
Cost units are what we are producing.
Anishma1 says
Thank you Sir, for this amazing lecture. 馃檪
Anishma1 says
And the free quizzes like this 馃檪
John Moffat says
Thank you for your comments 馃檪
Ashad2000 says
I got 100%
p.hungg says
I still wonder why $400 of direct labor is calculated in non-production overheads
NAJIBAA says
Non-production overheads are absorbed at rate of 120% of prime cost: Prime cost= direct material+direct labour= 300+400=700, then 120% of 700 means 840. In general, non-production overheads are absorbed per labour hour or machine hour, etc since what the question specifies for a base. In this example, it mentions, absorption is based on the rate of prime cost, so you need to follow what the question says.
FYI:
Choosing the appropriate absorption base
The different bases of absorption are as follows.
? A percentage of direct materials cost
? A percentage of direct labour cost
? A percentage of prime cost
? A rate per machine hour
? A rate per direct labour hour
? A rate per unit
? A percentage of factory cost (for administration overhead)
? A percentage of sales or factory cost (for selling and distribution overhead)
jojo99 says
I do not understand how you got 50 hours for #4?
dhasuhduah says
Total $400 direct labour and $8 per direct labour hour, divide it then you will get 50 hours
John Moffat says
馃檪
lokeshdh00 says
100% Correct
Disha@524 says
Sir can you please tell us the marks distribution as per the topic i. e Weitage as per topic for Exam?
John Moffat says
The ACCA does not give weightages for each topic.
waheedullaharify says
Q 3 is confusing
John Moffat says
It is a past real exam question (and is similar to one of the examples that I work through in my free lectures) 馃檪
safashaikh19 says
i didnt understand the 3rd question. do i have to prepare a cost card in it?
John Moffat says
No, the question just wants you to calculate the fixed overheads per unit for product M.
You need to calculate the overhead absorption rate for each of the 2 cost centres as I do in the free lectures, and then you can calculate the fixed overheads for product M.
safashaikh19 says
Thank you, sir. I think I need a lot of practice!
John Moffat says
You are welcome 馃檪
christafar says
100%