Learning curves

Ssharly11y ago
Please I have a multiple choice question in this topic. A company is intending to produce a new product. They have made two' test' units- the first of them took 8 hours to make, and the second took 6 hours. What is the learning rates? .87.5% .75% .25% .12.5%
John MoffatJohn MoffatTutor11y ago#1
Have you watched the free lecture on learning rates, because I go through this in the lecture. Since the average time for 2 units is 7 hours per unit, the learning rate is 7/8 = 87.5% (or 0.875)